Cost Variance
Also known as: cost variance
Definition
Cost variance is the difference between the actual cost and the expected, standard, or budgeted cost of an activity.
Detailed explanation
Variance analysis helps determine whether inefficiency, price changes, lower productivity, purchasing errors, or volume effects caused the difference. It is not enough to observe that cost increased; management must explain why and whether the cause is temporary or structural. It is a valuable control tool when budgets or standard costs are used.
Use cases
Identify cost overruns in production, purchasing, or services
Explain why actual cost differed from budget or standard
Take corrective action on efficiency, suppliers, or processes
Practical example
The standard cost of manufacturing a component was $120, but actual cost was $143. The variance requires review of scrap, inputs, productivity, and purchasing.